June 7, 2016 – 4th Middle School Update

At their June 7, 2016, Work Session an update on the JBMS project was presented to the WJCC School Board by Howard Collins, president of architectural firm Waller, Todd & Sadler, and Michael Hall, president and educational facility planner at Fanning Howey.

Mr. Collins said the project was on schedule to follow the below timeline:

Phase 1a (parking lot & new entrance for Central Office) May – August 2016
Phase 1b (JBMS design & construction) May 2016 – September 2018
Pre-final Design Documents (90%) May 20, 2016
Owner Review May 23 – June 6, 2016
Final Design Documents (100%) June 15, 2016
Permit Review June 15 – July 15, 2016
Bid Phase July 1 – August 4, 2016
Award August 16, 2016
Construction September 2016 – June 2018
Open September 2018