12/2/16 Construction Update

Work performed this week:

  • Completed earthwork in the sediment pond.
  • Completed installation of the underground sanitary pipe.
  • Continued interior and exterior wall footings by gym area.
  • Laid out masonry foundation walls.
  • Continued demolition of asphalt within the building pad.

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.