1/31/17 Construction Update

Work performed last week:

  • Continued footing and concrete masonry unit foundation walls in Units A and B
  • Continued concrete masonry unit walls in Unit B
  • Continued under-slab and in wall plumbing and electrical rough-in in Units B, C, and D
  • Continued underground storm pipe near the sediment pond

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

 