Work performed last week:

  • Began building pad preparation for the slab-on-grade in Units C and D
  • Continued interior concrete masonry unit foundation walls in Units A and B
  • Continued concrete masonry unit walls in Units B and D, and began walls in Unit A
  • Installed the fire line service pipe into the Fire Pump room
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units B, C, and D
  • Continued underground storm pipe towards the building
  • Resumed clearing trees on the West end of the property

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.