Williamsburg-James City County Public Schools News & Information

3/10/17 Construction Update

Work performed last week:

  • Constructed storm structure and set reinforced concrete pipe
  • Continued interior footing and foundation walls in Units A, B and C
  • Continued exterior and interior concrete masonry unit (concrete block) walls up to second floor level in Unit A and B
  • Continued exterior concrete masonry unit walls to four feet above the finished floor in Level 2 in Unit B
  • Metal door and window frames were delivered onsite
  • Continued under-slab and wall mechanical and electrical rough-in in Units A, B and C on Level 1

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.