Williamsburg-James City County Public Schools News & Information

3/17/17 Construction Update

Work performed last week:

  • Began storm structures and pipe along Longhill Road
  • Continued interior footings and foundation walls in Units A, B and C
  • Continued exterior and interior concrete masonry unit walls to Level 2 joist bearing in Units A and B
  • Continued under-slab and wall mechanical and electrical rough-in in Units A and B on Level 1
  • Began slab-on grade preparation in Unit A

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.