4/10/17 Construction Update

Work performed last week:

  • Continued interior and exterior footings and foundation walls in Units A and B
  • Continued interior walls on Level 1 in Units A, B and C to Level 2 joist bearing
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Continued slab-on-grade preparation and poured concrete in the classroom and collaboration area on April 8, 2017
  • Crane delivered for erecting the structural steel

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.