Work performed last week:

  • Cut and graded the subgrade and place porous sand fill subbase in the Auditeria
  • Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and D
  • Continued gymnasium walls on the North and East
  • Continued in-wall plumbing and electrical rough-in in Units A, B, C and D on Level 1
  • Began above ceiling mechanical and plumbing rough-in (pipe hangers) in Unit B on Level 1
  • Completed installation and inspected structural steel connections in Unit B supporting Level 2
  • Continued setting floor joists and corrugated metal decking in Unit B on Level 2
  • Installed structural steel studs on the decking in Unit B on Level 2 