5/5/17 Construction Update
Work performed last week:
- Excavated and poured footings in the Auditeria
- Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and D
- Continued gymnasium walls on the North end
- Continued in-wall plumbing and electrical rough-in in Units A, B and D on Level 1
- Completed installation and inspected structural steel connections in Unit B supporting Level 2
- Began setting corrugated metal decking in Unit B on Level 2
- Continued storm structures and pipe from SS#2-4 to SS#2-7 on the locker room side of the building
Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.