Work performed last week:

  • Poured the lowest two levels of the Auditeria floor
  • Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and D and set bearing plates
  • Grouted the Gymnasium walls at the high roof
  • Began mechanical room exterior walls
  • Completed floor joists and decking in Unit B2
  • Set structural steel lintels in Unit A on Level 1
  • Continued in-wall plumbing and electrical rough-in in Units A, B, C and D on Level 1
  • Began above ceiling mechanical, plumbing and electrical rough-in in Unit B
  • Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.