5/26/17 Construction Update

Work performed last week:

  • Poured the third level of the Auditeria floor
  • Poured the elevate concrete floor in Unit B on Level 2 last Saturday
  • Continued mechanical room exterior walls
  • Continued exterior and interior concrete masonry walls on Level 1 to Level 2 joist bearing in Units A and D
  • Grouted the Gymnasium walls at the high roof
  • Completed structural steel bracing in Unit B2
  • Started structural steel columns, beams and joists in Unit A supporting Level 2
  • Continued in-wall plumbing and electrical rough in in Units A, B, C and D on Level 1
  • Continued above ceiling mechanical, plumbing and electrical rough-in in Unit B1
  • Began wall and chase plumbing rough-in in Unit B2
  • Begin demolition of existing curb and asphalt in the parking lot at the corner of Longhill Road and Ironbound Road
    Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.