Work Performed this Week:

  • Poured the slab-on-grade surrounding the Auditeria. Remaining locations to pour include the stage and the receiving area
  • Constructed the mechanical room walls to roof bearing height
  • Continued CMU load-bearing walls in Unit B2
  • Continued above ceiling mechanical, electrical, and plumbing rough-in in Unit B1
  • Continued mechanical, electrical, and plumbing wall rough-in in Unit B2
  • Continued structural steel, joists, and decking in Unit A supporting Level 2
  • Began rough grading in the parking lot at the corner of Longhill Road and Ironbound Road