6/16/17 Construction Update

  • Completed and backfilled the foundation walls, and placed granular fill in preparation for the slab-on-grade pour at the Stage C102
  • Continued load-bearing CMU walls in Unit B2
  • Set steel lintels over the Unit B2 windows
  • Continued above ceiling mechanical, electrical, and plumbing rough-in in Unit B1
  • Continued mechanical, electrical, and plumbing wall rough-in in Unit B2
  • Continued electrical rough-in in Electric Room B118
  • Started above ceiling mechanical, electrical, and plumbing rough-in in Unit A1
  • Continued structural steel and decking in Unit A2
  • Set the Gymnasium roof joists
  • Continued rough grading in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.