6/22/17 – Construction Update

  • Poured the concrete slab at the Stage
  • Installed welded wire reinforcing in Unit A2 in preparation for the deck pour
  • Continued CMU load-bearing walls in Unit B2
  • Set steel lintels over the Unit B2 windows
  • Constructed CMU walls at the portal openings (doorway) between Units A1 and B1
  • Continued CMU load-bearing walls in Unit D
  • Continued above ceiling mechanical, electrical, and plumbing rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Unit B2
  • Completed structural steel, joists, and decking in Unit A supporting Level 2
  • Continue setting roof joists and decking in Unit C at the Gymnasium
  • Structural steel beams for Unit B3 were delivered
  • Cleared the trees along Ironbound Road
  • Proof-rolled the East parking lot subgrade to test compaction of the existing soil
  • Obtained easement paperwork for Dominion Energy

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.