6/29/17 – Construction Update

  • Poured the Unit A2 floor on June 27, 2017
  • Continued CMU load-bearing walls in Unit B2
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Constructed CMU walls at the portal openings (doorway) between Units A1 and B1
  • Continued CMU load-bearing walls in Unit D
  • Continued above ceiling mechanical, electrical, and plumbing rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Unit B2
  • Completed roof joists and decking in Unit C at the Gymnasium
  • An above ceiling coordination meeting was held on June 27, 2017 for all MEP work in Units B1 and A1
  • Resumed installation of the underground storm system on the West side of the building

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.