7/7/2017 – Construction Update

Work Performed this Week:

  • Completed the final portion of the slab-on-grade concrete
  • Formed floor slab and set reinforcing bar at the Unit B2 portal openings
  • Completed CMU load-bearing walls in Unit B2 and continued walls in Unit A2
  • Began non-bearing masonry walls in Unit B1
  • Began structural steel beams and joists supporting Unit B3
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued CMU load-bearing walls in Unit C Locker Rooms
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B2, A2, and C
  • Set roof joists in Unit C Mechanical Room
  • Continued installation of the underground storm system on the West side of the building
  • Continued filling and grading in the East parking lot
  • Staked out the curb in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.