7/20/17 – Construction Update

Work Performed this Week:

  • Poured the portal opening floor slabs in Unit B2
  • Backfilled and installed vapor barrier at the Stage steps and ramp
  • Continued load-bearing masonry walls in Units A2 and C
  • Continued non-bearing masonry walls in Units B1 and A1
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B1, A1, A2, and C
  • Continued structural steel beams, joists, and decking supporting Unit B3
  • Continued filling and grading in the East parking lot
  • Began stone subbase in the East parking lot
  • Laid out curb and gutter in the East parking lot
  • Continued the underground storm on the North side of the building along the bus loop toward Longhill Road

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.