7/27/17 – Construction Update

Work Performed this Week:

  • Poured the Stage steps and ramp completing all slab-on-grade work within the building
  • Continued load-bearing masonry walls in Units A2, C, and D
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B1, A2, and C
  • Completed structural steel beams, joists, and decking supporting Unit B3
  • Completed steel joists and decking supporting the mechanical room roof
  • Began structural steel in Unit A3
  • Continued work on the exterior mockup panel with installation of through-wall flashings and sealant joints
  • Continued stone subbase in the East parking lot
  • Completed layout for curb and gutter in the East parking lot
  • Continued the underground storm on the North side of the building along the bus loop toward Longhill Road

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.