7/24/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and decking in Unit A3
  • Continued load-bearing masonry in Units B3, C, and D
  • Continued forming the Gathering Stairs and installing reinforcing bar
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Unit B2
  • Began above ceiling electrical rough-in in Units B2 and A2
  • Continued chilled water piping in Units A1 and B1
  • Continued installing sprinkler pipe and heads in Unit B1
  • Continued SPF insulation on the exterior walls in Units B and C
  • Completed installation of the gymnasium roof
  • Continued grading and placed stone subbase along the access road between the bus loop and Central Office parking lot
  • Backfilled the new curb in the East parking lot
  • Began underground rough-in for site lighting in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.