Work Performed this Week:

  • Completed structural steel, joists, and decking in Unit A3
  • Started structural steel in Unit C Auditeria
  • Continued load-bearing masonry in Units B3, C, and D
  • Continued forming the Gathering Stairs and installing reinforcing bar
  • Poured the elevated deck in Unit A3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1, A1, and B2
  • Continued above ceiling electrical rough-in in Units B2 and A2
  • Continued chilled water piping in Units A1 and B1
  • Continued installing sprinkler pipe, drops, and heads in Unit A1
  • Backfilled the new curb in the East parking lot
  • Relocated contractor parking to the East parking lot
  • Continued underground rough-in for site lighting in the East parking lot
  • Continued asphalt demolition along Longhill Road
  • Resumed storm system from SS#2-9 toward SS#2-10