9/8/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and joists in Units C and D
  • Continued load-bearing masonry in Units B3, C, and D
  • Poured a portion of the Gathering Stairs
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1, A1, B2, and started in Unit A2
  • Continued chilled water piping in Units A1 and B1
  • Completed the storm drain to SS#2-10
  • Resumed fire main along Longhill Road
  • Continued underground rough-in for site lighting in the East parking lot and poured the light pole bases

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.