9/15/2017 – Construction Update

Work Performed this Week:

  • Continued load-bearing masonry in Units B3, C, and D
  • Poured the remainder of the Gathering Stairs
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1, A1, B2, and A2
  • Continued chilled water piping in Units A1, B1, and B2
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Continued fire main to the mechanical room
  • Installed underground conduit across the bus loop for site lighting and power to out buildings

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.