9/29/2017 – Construction Update

Work Performed this Week:

  • Continued roof structural steel and joists in Unit B
  • Continued load-bearing masonry in Units A3, C, and D
  • Continued veneer brick on the Unit A low roof
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B2, A2, B1, and A1
  • Continued chilled water piping in the mechanical chases
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Tested the fire main to the mechanical room
  • Installed the domestic water line to the mechanical room
  • Began the domestic water pipe to the Cooley Field spigot
  • Began under-slab conduit to the transformer in the mechanical yard
  • Cut to subgrade in the North parking lot, formed and poured curb, and placed stone subbase
  • Began grading the bus loop subgrade
  • Set electrical switch gear on the house keeping pads

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.