10/5/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began exterior metal framing in Unit B
  • Continued load-bearing masonry in Units A3, C, and D
  • Continued veneer brick on the Unit A low roof
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B2, A2, B1, and A1
  • Completed chilled water piping in the mechanical chases through the third floor
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Completed the domestic water line to the mechanical room
  • Installed the domestic water pipe to the Cooley Field spigot
  • Installed the storm structure and pipe at SS#3-2 near Longhill Road
  • Continued under-slab rough-in in the mechanical yard
  • Continued grading the bus loop subgrade

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.