10/20/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Continued installing roof deck in the Unit C locker rooms
  • Continued exterior metal framing on the high walls on the gymnasium
  • Continued load-bearing masonry in Units A, B3, and C
  • Continued exterior brick veneer in Unit B1
  • Began installing clips for the exterior composite wall panels on the high walls of the gymnasium
  • Continued installing sprinkler pipe in Units B2 and A2
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units A1 and B3
  • Continued above ceiling domestic water piping in Units B and A
  • Continued electrical above ceiling rough-in in Units B3
  • Continued grading the bus loop subgrade
  • Installed rain leaders from Unit B to storm structure SS#2-10

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.