10/20/2017 – Construction Update
Work Performed this Week:
- Continued structural steel and roof decking in Unit B
- Continued installing roof deck in the Unit C locker rooms
- Continued exterior metal framing on the high walls on the gymnasium
- Continued load-bearing masonry in Units A, B3, and C
- Continued exterior brick veneer in Unit B1
- Began installing clips for the exterior composite wall panels on the high walls of the gymnasium
- Continued installing sprinkler pipe in Units B2 and A2
- Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
- Continued hanging ductwork in Units A1 and B3
- Continued above ceiling domestic water piping in Units B and A
- Continued electrical above ceiling rough-in in Units B3
- Continued grading the bus loop subgrade
- Installed rain leaders from Unit B to storm structure SS#2-10
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.