11/3/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Units B and A
  • Continued exterior parapet framing in Unit B
  • Continued load-bearing masonry in Unit C
  • Continued interior masonry in Unit B2
  • Continued exterior brick veneer in Units B and C
  • Continued installing clips for the exterior composite wall panels in Unit B
  • Installed PVC roofing on the mechanical room roof
  • Continued installing sprinkler pipe in Unit B3 and gymnasium
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1 and B3
  • Air handling units delivered
  • Continued above ceiling mechanical piping in Unit A1
  • Continued chase wall plumbing in Unit B3
  • Continued electrical above ceiling rough-in in Unit B3
  • Placed subbase stone in the bus loop
  • Installed rain leaders from Unit C to the storm structures
  • Continued spray polyurethane foam insulation throughout
  • Removed the existing scoreboard, net and poles, and flagpole

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.