12/1/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Continued exterior parapet framing in Units B and A
  • Continued load-bearing masonry in Unit D and C
  • Continued exterior brick veneer in Unit B
  • Set windows in the Unit B2 classrooms
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B and A
  • Formed and pour equipment pads, and stage steps and ramp
  • Continued above ceiling mechanical piping in Unit B3
  • Continued drain, waste, and vent piping in Units B and A
  • Continued above ceiling electrical rough-in in Units B3 and A3
  • Continued underground conduit in the mechanical yard for the generators
  • Continued rain leader piping in Unit A
  • Continued electrical above ceiling rough-in in Units B and A
  • Continued work on the bus loop
  • Installed the power service line conduit from the existing transformer at the Annex to the new school

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.