12/15/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Continued exterior parapet framing in Unit A
  • Continued load-bearing masonry in Units D and C
  • Continued interior masonry in Unit B
  • Continued exterior brick veneer in Units B, C, and D
  • Completed interior framing in Units B3 and A3
  • Began interior framing in Units B2 and A2
  • Continued roofing in Unit A
  • Continued setting windows in the Unit B
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Installed steel pipe to the boilers in the mechanical room
  • Continued above ceiling mechanical piping in Unit B3
  • Variable air volume (VAV) equipment was delivered
  • Continued hanging ductwork in Units B and A
  • Continued drain, waste, and vent piping in Units B and A
  • Continued above ceiling electrical rough-in in Units B3 and A3
  • Connected the electrical switchgear components
  • Poured concrete in the metal pan stairs in Unit B Stair BS-2
  • Set the handrails in Stair BS-2
  • Began applying the first coat of bock filler in Units B3 and B2

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.