12/22/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Installed the structural supports for the operable partition walls in Unit B
  • Continued exterior parapet framing in Unit A
  • Completed load-bearing masonry in Units D and C
  • Continued interior masonry in Unit B
  • Continued exterior brick veneer in Units B and C
  • Continued spray polyurethane foam insulation in Units B and C
  • Completed interior framing in Units B2 and A2
  • Began interior framing in Units B1
  • Continued setting windows in the Unit B
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Installed steel pipe to the boilers in the mechanical room
  • Set mechanical equipment curbs on the Unit C roof
  • Continued above ceiling domestic water piping in Unit B
  • Continued hanging ductwork in Units B and A
  • Continued above ceiling and framed wall electrical rough-in in Units B and A
  • Unit B3 and A3 electrical rough-in was inspected by the City
  • Continued connecting the electrical switchgear components
  • Excavated and poured the mechanical yard screen wall footings
  • Continue installing the metal pan stair structure in Stair BS-1

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.