1/12/2018 – Construction Update
Work Performed this Week:
- Excavated and poured column footings for the student entrance canopy
- Continued exterior framing in Units A and C
- Laid veneer brick on the North and West elevations of Unit C
- Continued spray polyurethane foam (SPF) insulation on the exterior walls in Units D and C
- Continued correcting the elevation deficiency on the operable partition wall support framing in Unit B
- Continued installing joist bridging in Unit C
- Installed vapor barrier on the Unit D roof
- Continued setting exterior windows in Unit A
- Continued interior framing, hanging gypsum board, sound insulation, and finishing in Unit B3
- Installed the head track for the operable partition walls in Unit B3
- Continued priming masonry walls in Unit AB3
- Continued wall and above ceiling rough-in and pulling wire in Unit A and B
- Continued hanging VAVs and ductwork in Units A and B
- Continued drain, waste, and vent piping in Unit B; City test passed
- Continued steel hydronic piping in Unit C
- Installed the metal pan stairs and railings in Stair AS-1
- Completed final welding of handrails in Stair BS-2
- OPCC met with Dominion Energy (DE) to coordinate and schedule the installation of the electrical service line to the school; installation expected in February 2018
Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.