3/5/2018 – Construction Update

Work Performed this Week:

  • Resumed interior brick in Unit A1
  • Continued non-load bearing interior CMU walls in throughout
  • Poured concrete locker pads in the locker rooms
  • Poured the mechanical yard equipment pads and slab-on-grade
  • Continued adjusting the operable partition wall support steel in Unit B
  • Installed structural steel and roof decking at the student entrance canopy
  • Continued exterior framing in Unit A
  • Continued installing exterior windows in Units A1, D, and C
  • Continued curtainwall framing in Unit B
  • Installed exterior composite wall panels and flashings
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB3, AB2, and AB1
  • Continued priming and painting in Units B3 and B2
  • Continued ceramic wall tile and porcelain floor tile in Unit B
  • Continued final connections to the VAVs in Units A and B
  • Continued hanging VAVs and ductwork in Units C, and D
  • Continued insulating low and medium pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit D
  • Continued steel hydronic piping in Unit C
  • Installed lights in the ceiling grid in Unit AB3
  • Continued installing ceiling grid in Unit B2

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.