4/23/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, and C 
  • Continued priming and painting in Units B and C 
  • Completed ceramic tile in the locker rooms and food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Set the cooling towers on the support framing in the mechanical yard 
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A, B, and C 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Permanent power connected and meter set 
  • Permanent service line connected and meter set 
  • Began installing science lab casework 
  • Began installing gymnasium equipment 
  • Installed the cooler and freezer in food service 
  • Sitework resumed with sidewalks poured in the East parking lot 
  • Bus fuel tank pad formed and ready for the concrete 
  • Continued pulling data wiring in Unit B1 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.