5/28/2018 – Construction Update

Work Performed this Week:

  • Continued brickwork at the mechanical yard wall and correcting interior masonry items 
  • Installed tube steel for the Gathering Stairs and miscellaneous steel supports for the stage partition wall 
  • Continued glazing the radius windows in Unit A 
  • Installed glass partition wall track in Unit B3 
  • Continued setting exterior frames and doors 
  • Hanging exterior composite metal panels in Units B and A 
  • Continued framing interior walls, hanging gypsum board, and finishing in Units A1 and C 
  • Continued ceiling grid and painting in Units C and D 
  • Continued tilework 
  • Delivered and installed food service equipment 
  • Continued installing ductwork and mechanical pipe in Units C and D 
  • Continued mechanical pipe in the mechanical room and yard 
  • Continued flushing and filtering the mechanical pipe and testing water quality 
  • Installed the split unit air conditioners in the IT closets 
  • Completed electrical connections the mechanical equipment 
  • Continued pulling fire alarm wiring in Units C and D 
  • Continued terminating electrical devices in Units A and B 
  • Continued terminating control wiring in the mechanical room and rooftop units 
  • Continued backfilling the curb and grading the ball field 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.