8/11/17 – Construction Update

Work Performed this Week: Continued structural steel, joists, and decking in Unit A3 Started load-bearing masonry in Unit B3 Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses Continued hanging ductwork in Units B1 and A1, and began ductwork in Unit B2 Resumed chilled water piping in Unit A1 Poured the elevated deck […]

8/4/17 – Construction Update

Work Performed this Week: Completed stone subbase in the East parking lot Completed load-bearing masonry in Unit A2 Continued load-bearing masonry walls in Units C and D in music, locker rooms and stage Completed elevated deck preparations in Unit B3 Completed the spray-applied polyurethane foam (SPF) mockup at the sample panel Continued the 10-gauge metal […]

7/27/17 – Construction Update

Work Performed this Week: Poured the Stage steps and ramp completing all slab-on-grade work within the building Continued load-bearing masonry walls in Units A2, C, and D Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1 Continued mechanical, electrical, and plumbing wall rough-in in Units B1, A2, and C Completed […]

7/20/17 – Construction Update

Work Performed this Week: Poured the portal opening floor slabs in Unit B2 Backfilled and installed vapor barrier at the Stage steps and ramp Continued load-bearing masonry walls in Units A2 and C Continued non-bearing masonry walls in Units B1 and A1 Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and […]

7/14/2017 – Construction Update

Work Performed this Week: Formed floor slab and set reinforcing bar at the Unit B2 portal openings Formed the ramp from the Auditeria to the Stage Continued load-bearing masonry walls in Units A2 and C Locker Rooms Continued non-bearing masonry walls in Unit B1 Continued structural steel beams, joists, and decking supporting Unit B3 Continued […]