Work Performed this Week:

  • Completed preparation of the building pad in music, gym, auditeria, and kitchen.
  • Began and completed asphalt demolition in the administration and classroom area.
  • Continued footings in music, gym, auditeria, and kitchen (Area D)
  • Installed a construction road around the perimeter of the building pad.
  • Mechanical and electrical sub-contractors mobilized
  • Laid out under-slab mechanical work and installed pipe sleeves across footings in music, gym, auditeria, and kitchen

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.