12/22/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Installed the structural supports for the operable partition walls in Unit B
  • Continued exterior parapet framing in Unit A
  • Completed load-bearing masonry in Units D and C
  • Continued interior masonry in Unit B
  • Continued exterior brick veneer in Units B and C
  • Continued spray polyurethane foam insulation in Units B and C
  • Completed interior framing in Units B2 and A2
  • Began interior framing in Units B1
  • Continued setting windows in the Unit B
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Installed steel pipe to the boilers in the mechanical room
  • Set mechanical equipment curbs on the Unit C roof
  • Continued above ceiling domestic water piping in Unit B
  • Continued hanging ductwork in Units B and A
  • Continued above ceiling and framed wall electrical rough-in in Units B and A
  • Unit B3 and A3 electrical rough-in was inspected by the City
  • Continued connecting the electrical switchgear components
  • Excavated and poured the mechanical yard screen wall footings
  • Continue installing the metal pan stair structure in Stair BS-1

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

12/15/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Continued exterior parapet framing in Unit A
  • Continued load-bearing masonry in Units D and C
  • Continued interior masonry in Unit B
  • Continued exterior brick veneer in Units B, C, and D
  • Completed interior framing in Units B3 and A3
  • Began interior framing in Units B2 and A2
  • Continued roofing in Unit A
  • Continued setting windows in the Unit B
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Installed steel pipe to the boilers in the mechanical room
  • Continued above ceiling mechanical piping in Unit B3
  • Variable air volume (VAV) equipment was delivered
  • Continued hanging ductwork in Units B and A
  • Continued drain, waste, and vent piping in Units B and A
  • Continued above ceiling electrical rough-in in Units B3 and A3
  • Connected the electrical switchgear components
  • Poured concrete in the metal pan stairs in Unit B Stair BS-2
  • Set the handrails in Stair BS-2
  • Began applying the first coat of bock filler in Units B3 and B2

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

12/8/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Continued exterior parapet framing in Units B and A
  • Continued load-bearing masonry in Unit D and C
  • Continued interior masonry in Unit B
  • Continued exterior brick veneer in Units B, C, and D
  • Set windows in the Unit B3 classrooms
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Set water pumps in the mechanical room
  • Continued hanging ductwork in Units B and A
  • Continued above ceiling mechanical piping in Unit B3
  • Continued drain, waste, and vent piping in Units B and A
  • Continued above ceiling electrical rough-in in Units B3 and A3
  • Continued underground conduit in the mechanical yard for the generators
  • Resumed installation of the stair in Unit B
  • Sitework is on hold until Spring 2018

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

12/1/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units C and D
  • Continued exterior parapet framing in Units B and A
  • Continued load-bearing masonry in Unit D and C
  • Continued exterior brick veneer in Unit B
  • Set windows in the Unit B2 classrooms
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B and A
  • Formed and pour equipment pads, and stage steps and ramp
  • Continued above ceiling mechanical piping in Unit B3
  • Continued drain, waste, and vent piping in Units B and A
  • Continued above ceiling electrical rough-in in Units B3 and A3
  • Continued underground conduit in the mechanical yard for the generators
  • Continued rain leader piping in Unit A
  • Continued electrical above ceiling rough-in in Units B and A
  • Continued work on the bus loop
  • Installed the power service line conduit from the existing transformer at the Annex to the new school

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

11/17/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and roof decking in Units B, A, C, and D
  • Continued exterior parapet framing in Unit B
  • Framed the West exterior wall in Unit A3
  • Continued load-bearing masonry in Unit C
  • Continued exterior brick veneer in Unit B
  • Set windows in the Unit B1 classrooms
  • Continued installing sprinkler pipe in Unit B3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B and A
  • Formed and pour equipment pads
  • Set mechanical equipment on the equipment pads in the mechanical room
  • Continued above ceiling mechanical piping in Unit B3
  • Continued drain, waste, and vent piping in Unit A3
  • Set the roof drains in Unit A
  • Continued electrical above ceiling rough-in in Units B and A
  • Connected the rain leaders from Units A and D to the storm structures
  • Drilled the underground electrical service line conduit from the existing transformer at the Annex toward the new school

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

11/10/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Units B and A
  • Continued exterior parapet framing in Unit B
  • Continued load-bearing masonry in Unit C
  • Continued interior masonry in Unit B2
  • Continued exterior brick veneer in Units B and C
  • Resumed roofing in Unit B
  • Continued installing clips for the exterior composite wall panels in Unit B
  • Continued installing sprinkler pipe in Unit C
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1 and B3
  • Air handling units delivered
  • Air handler set in the Unit A3 mechanical room
  • Continued above ceiling mechanical piping in Unit B3
  • Continued drain, waste, and vent piping in Unit B1
  • Continued electrical above ceiling rough-in in Unit B3
  • Installed rain leaders from Unit D to the storm structures
  • Continued spray polyurethane foam insulation in Unit B
  • Private underground utilities were marked for installation of the Dominion Energy service line, telecom conduit, and the new scoreboard at Cooley Field
  • Rain and wet site conditions impacted masonry work, steel, and roofing

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

11/3/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Units B and A
  • Continued exterior parapet framing in Unit B
  • Continued load-bearing masonry in Unit C
  • Continued interior masonry in Unit B2
  • Continued exterior brick veneer in Units B and C
  • Continued installing clips for the exterior composite wall panels in Unit B
  • Installed PVC roofing on the mechanical room roof
  • Continued installing sprinkler pipe in Unit B3 and gymnasium
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1 and B3
  • Air handling units delivered
  • Continued above ceiling mechanical piping in Unit A1
  • Continued chase wall plumbing in Unit B3
  • Continued electrical above ceiling rough-in in Unit B3
  • Placed subbase stone in the bus loop
  • Installed rain leaders from Unit C to the storm structures
  • Continued spray polyurethane foam insulation throughout
  • Removed the existing scoreboard, net and poles, and flagpole

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/27/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began roof steel and joists in Unit A
  • Continued installing roof deck in the Unit C locker rooms
  • Continued exterior metal framing on the high walls on the gymnasium
  • Continued load-bearing masonry in Units A, B3, and C
  • Continued exterior brick veneer in Unit B1
  • Continued installing clips for the exterior composite wall panels on the high walls of the gymnasium
  • Roofing material delivered for Unit B
  • Continued installing sprinkler pipe in Unit B3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1 and B3
  • Cooling towers delivered
  • Continued above ceiling domestic water piping in Units B and A
  • Continued electrical above ceiling rough-in in Units B3
  • Placed subbase stone in the bus loop
  • Installed rain leaders from Unit B to storm structure SS#2-10
  • Made the final domestic water connection at the building

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/20/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Continued installing roof deck in the Unit C locker rooms
  • Continued exterior metal framing on the high walls on the gymnasium
  • Continued load-bearing masonry in Units A, B3, and C
  • Continued exterior brick veneer in Unit B1
  • Began installing clips for the exterior composite wall panels on the high walls of the gymnasium
  • Continued installing sprinkler pipe in Units B2 and A2
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units A1 and B3
  • Continued above ceiling domestic water piping in Units B and A
  • Continued electrical above ceiling rough-in in Units B3
  • Continued grading the bus loop subgrade
  • Installed rain leaders from Unit B to storm structure SS#2-10

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/13/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began installing roof decking in Unit C locker rooms
  • Continued exterior metal framing
  • Continued load-bearing masonry in Units A3 and B3
  • Started installing sprinkler pipe in Units B2 and A2
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Unit C in the gymnasium
  • Continued above ceiling domestic water piping in Units B1 and A1
  • Chillers were delivered and set in the mechanical room
  • Set mechanical equipment curbs on the mechanical room roof
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Continued rough-in in the main electrical room in Unit C
  • Continued grading the bus loop subgrade

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.