Work performed last week:

  • Continued footing and concrete masonry unit foundation walls in Units A and B.
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units C and D.
  • Began in-wall electrical rough-in in Unit B.
  • Continued concrete masonry unit walls at the gymnasium and begin concrete masonry unit walls in Unit B.
  • Set the elevator sleeve.
  • Continue underground storm pipe from the existing structure to the sediment pond near the
    home team locker room.

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections