2/24/17 Construction Update

Work performed last week:

  • Removed stumps and debris from the West side of the site
  • Installed the gabion baskets (stone wall) in the sediment pond, fine graded, and seeded which completed the installation of the storm water basin
  • Poured the slab-on-grade in Units C and D
  • Continued exterior and interior concrete masonry unit walls to scaffold height in Units C and D
  • Laid interior concrete masonry unit foundation walls in Food Service
  • Continued exterior concrete masonry unit walls to second floor joist bearing in Unit B
  • Continued exterior and interior concrete masonry unit walls to scaffold height in Unit A
  • Delivered steel lintels and bearing plates, and set bearing plates in Unit B
  • Continued under-slab PVC plumbing and electrical in Units B and A
  • Continued mechanical and electrical rough-in in the equipment room
  • Continued under-slab rough-in for food service equipment
  • Continue plumbing and electrical wall rough-in in Units D, C, B and A

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

2/17/17 Construction Update

Work performed last week:

  • Continued clearing trees on the West end of the property
  • Connected an 8-inch fire line to the City’s main water line on Ironbound Road
  • Completed the storm system to SS#2-4 at the corner of Cooley Field
  • Grouted the exterior concrete masonry unit walls to the first floor lintel height in Unit B and to scaffold height in Unit A
  • Continued exterior concrete masonry unit walls in Unit A and B
  • Prepared and poured the slab-on-grade in the Gymnasium
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units B, C and D
  • Completed the underground secondary electrical feed conduit in the mechanical area
  • Completed the sprinkler access slab in Fire Pump room

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

2/10/17 Construction Update

Work performed last week:

  • Began building pad preparation for the slab-on-grade in Units C and D
  • Continued interior concrete masonry unit foundation walls in Units A and B
  • Continued concrete masonry unit walls in Units B and D, and began walls in Unit A
  • Installed the fire line service pipe into the Fire Pump room
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units B, C, and D
  • Continued underground storm pipe towards the building
  • Resumed clearing trees on the West end of the property

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

Photos

 

 

1/31/17 Construction Update

Work performed last week:

  • Continued footing and concrete masonry unit foundation walls in Units A and B
  • Continued concrete masonry unit walls in Unit B
  • Continued under-slab and in wall plumbing and electrical rough-in in Units B, C, and D
  • Continued underground storm pipe near the sediment pond

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

 