3/24/17 Construction Update

Work performed last week:

  • Set storm structures and reinforced concrete pipe at the corner of Ironbound Road and Longhill Road
  • Excavated for installation of the fire line on Ironbound Road
  • Continued interior footings and foundation walls in Units A, B and C
  • Continued exteriior and interior walls on Level 1 in Units A and B
  • Continued under-slab plumbing and electrical rough-in in Units A, B and C
  • Poured concrete slab-on grade in Unit A

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

 

 

 

3/17/17 Construction Update

Work performed last week:

  • Began storm structures and pipe along Longhill Road
  • Continued interior footings and foundation walls in Units A, B and C
  • Continued exterior and interior concrete masonry unit walls to Level 2 joist bearing in Units A and B
  • Continued under-slab and wall mechanical and electrical rough-in in Units A and B on Level 1
  • Began slab-on grade preparation in Unit A

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

 

3/10/17 Construction Update

Work performed last week:

  • Constructed storm structure and set reinforced concrete pipe
  • Continued interior footing and foundation walls in Units A, B and C
  • Continued exterior and interior concrete masonry unit (concrete block) walls up to second floor level in Unit A and B
  • Continued exterior concrete masonry unit walls to four feet above the finished floor in Level 2 in Unit B
  • Metal door and window frames were delivered onsite
  • Continued under-slab and wall mechanical and electrical rough-in in Units A, B and C on Level 1

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

3/3/17 Construction Update

Work performed last week:

  • Placed asphalt in the fire line connection on Ironbound Road
  • Continued slab-on-grade preparation in Units A and B
  • Continued footings in Units A and B
  • Continue interior foundation walls in Units A and B
  • Installed steel lintels and bearing plates in Unit B
  • Continued exterior concrete masonry unit walls (the concrete block walls visible in all the photos) in Unit B to four feet above the Level 2 floor line
  • Completed under-slab plumbing in Unit C Food Service
  • Continued under-slab mechanical and electrical rough-in in the mechanical rooms
  • Continued mechanical and electrical wall rough-in in Units A and B on Level 1

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.