4/14/17 Construction Update

Work performed last week:

  • Continued interior and exterior footings and foundation walls in Units A and B
  • Continued interior walls on Level 1 in Units A, B, and C to Level 2 joist bearing
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Continued slab-on-grade preparation and poured concrete in science/restroom area in Unit B, and the entrance commons in Unit A on April 15th
  • Delivered and set the elevator jack
  • Set steel beam over opening between the gymnasium and stage
  • Set reinforced concrete storm pipe and tied new storm system into the City’s existing system at the corner of Ironbound Road and Longhill Road
  • Received the check valve for the fire line and installed the valve near Ironbound Road

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

 

 

 

4/10/17 Construction Update

Work performed last week:

  • Continued interior and exterior footings and foundation walls in Units A and B
  • Continued interior walls on Level 1 in Units A, B and C to Level 2 joist bearing
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Continued slab-on-grade preparation and poured concrete in the classroom and collaboration area on April 8, 2017
  • Crane delivered for erecting the structural steel

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

 

 

 

3/31/17 Construction Update

Work performed last week:

  • Continued setting storm structures and reinforced concrete pipe at the corner of Ironbound Road and Longhill Road
  • Continued interior footings and foundation walls in Units A, B, and C
  • Continued exterior and interior walls on Level 1 in Units A, B and C
  • Poured the elevator footing and foundation walls
  • Continued under-slab and in-wall plumbing and electrical rough-in in Units A, B and C on Level 1

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.