4/28/17 Construction Update

Work performed last week:

  • Continued exterior and interior concrete masonry walls on Level 1 to the Level 2 joist bearing in Units A
  • Continued gymnasium walls
  • Continued in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Complete slab-on-grade preparation in the Unit C mechanical rooms and food service area and pour concrete
  • Structural steel delivered for Unit B
  • Began setting structural steel columns, beams and joists in Unit B on Levels 1 and 2
  • Continued the fire line from Ironbound Road along Longhill Road toward the building

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.

 

 

 

 

 

 

 

 

 

 

4/21/17 Construction Update

Work performed last week:

  • Excavated and poured exterior column footings for canopies in Unit A
  • Continued exterior and interior concrete masonry unit walls on Level 1 to Level 2 joist bearing in Units A and B
  • Continued gymnasium concrete masonry unit walls
  • Continued in-wall plumbing and electrical rough-in in Units A and B on Level 1
  • Completed under-slab and in-wall plumbing and electrical rough-in in the mechanical room and food service area
  • Continued slab-on-grade preparation in the mechanical room and food service area
  • Delivered structural steel
  • Continued storm structures and pipe along Longhill Road
  • Continued the fire line from Ironbound Road toward the building

Note: Areas D & C are the single story section of the school. That includes the gym, cafeteria, kitchen, music, art and fitness rooms. Areas A & B are the 3-story classroom sections.