7/27/17 – Construction Update

Work Performed this Week:

  • Poured the Stage steps and ramp completing all slab-on-grade work within the building
  • Continued load-bearing masonry walls in Units A2, C, and D
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B1, A2, and C
  • Completed structural steel beams, joists, and decking supporting Unit B3
  • Completed steel joists and decking supporting the mechanical room roof
  • Began structural steel in Unit A3
  • Continued work on the exterior mockup panel with installation of through-wall flashings and sealant joints
  • Continued stone subbase in the East parking lot
  • Completed layout for curb and gutter in the East parking lot
  • Continued the underground storm on the North side of the building along the bus loop toward Longhill Road

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

7/20/17 – Construction Update

Work Performed this Week:

  • Poured the portal opening floor slabs in Unit B2
  • Backfilled and installed vapor barrier at the Stage steps and ramp
  • Continued load-bearing masonry walls in Units A2 and C
  • Continued non-bearing masonry walls in Units B1 and A1
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B1, A1, A2, and C
  • Continued structural steel beams, joists, and decking supporting Unit B3
  • Continued filling and grading in the East parking lot
  • Began stone subbase in the East parking lot
  • Laid out curb and gutter in the East parking lot
  • Continued the underground storm on the North side of the building along the bus loop toward Longhill Road

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

7/14/2017 – Construction Update

Work Performed this Week:

  • Formed floor slab and set reinforcing bar at the Unit B2 portal openings
  • Formed the ramp from the Auditeria to the Stage
  • Continued load-bearing masonry walls in Units A2 and C Locker Rooms
  • Continued non-bearing masonry walls in Unit B1
  • Continued structural steel beams, joists, and decking supporting Unit B3
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B2, A2, and C
  • Continued installation of the underground storm system on the North side of the building near the Gymnasium
  • Set the grease interceptor
  • Continued filling and grading in the East parking lot
  • Staked out the curb in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

7/7/2017 – Construction Update

Work Performed this Week:

  • Completed the final portion of the slab-on-grade concrete
  • Formed floor slab and set reinforcing bar at the Unit B2 portal openings
  • Completed CMU load-bearing walls in Unit B2 and continued walls in Unit A2
  • Began non-bearing masonry walls in Unit B1
  • Began structural steel beams and joists supporting Unit B3
  • Continued above ceiling mechanical, electrical, and plumbing (MEP) rough-in in Units B1 and A1
  • Continued CMU load-bearing walls in Unit C Locker Rooms
  • Continued mechanical, electrical, and plumbing wall rough-in in Units B2, A2, and C
  • Set roof joists in Unit C Mechanical Room
  • Continued installation of the underground storm system on the West side of the building
  • Continued filling and grading in the East parking lot
  • Staked out the curb in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.