7/24/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and decking in Unit A3
  • Continued load-bearing masonry in Units B3, C, and D
  • Continued forming the Gathering Stairs and installing reinforcing bar
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Unit B2
  • Began above ceiling electrical rough-in in Units B2 and A2
  • Continued chilled water piping in Units A1 and B1
  • Continued installing sprinkler pipe and heads in Unit B1
  • Continued SPF insulation on the exterior walls in Units B and C
  • Completed installation of the gymnasium roof
  • Continued grading and placed stone subbase along the access road between the bus loop and Central Office parking lot
  • Backfilled the new curb in the East parking lot
  • Began underground rough-in for site lighting in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

7/18/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and decking in Unit A3
  • Continued load-bearing masonry in Units B3, C, and D
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1, A1, and B2
  • Continued chilled water piping in Unit A1
  • Continued foundation brick and masonry flashing in Unit B
  • Began SPF insulation in Unit B
  • Continued installation of the gymnasium roof
  • Continued grading and placed stone subbase along the access road between the bus loop and Central Office parking lot
  • Installed concrete curb in the East parking lot
  • Backfilled the new curb in the East parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

8/11/17 – Construction Update

Work Performed this Week:

  • Continued structural steel, joists, and decking in Unit A3
  • Started load-bearing masonry in Unit B3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1 and A1, and began ductwork in Unit B2
  • Resumed chilled water piping in Unit A1
  • Poured the elevated deck in Unit B3 and portal slab in Unit B2
  • Continued ball field subgrade grading
  • Continued foundation brick and masonry flashing in Unit B
  • Started installation of the gymnasium roof
  • Began rough grading along the access road between the bus loop and Central Office parking lot

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

8/4/17 – Construction Update

Work Performed this Week:

  • Completed stone subbase in the East parking lot
  • Completed load-bearing masonry in Unit A2
  • Continued load-bearing masonry walls in Units C and D in music, locker rooms and stage
  • Completed elevated deck preparations in Unit B3
  • Completed the spray-applied polyurethane foam (SPF) mockup at the sample panel
  • Continued the 10-gauge metal framing at the window openings in Unit B
  • Installed masonry flashing at the base of the walls in Unit B
  • Installed window head flashing in Unit B
  • Continued above ceiling electrical rough-in in Units B1 and A1
  • Continued ductwork in Units B1 and A1
  • Began rough-grading in the ball field
  • Installed the metal stair pans in Classroom stair tower

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.