9/29/2017 – Construction Update

Work Performed this Week:

  • Continued roof structural steel and joists in Unit B
  • Continued load-bearing masonry in Units A3, C, and D
  • Continued veneer brick on the Unit A low roof
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B2, A2, B1, and A1
  • Continued chilled water piping in the mechanical chases
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Tested the fire main to the mechanical room
  • Installed the domestic water line to the mechanical room
  • Began the domestic water pipe to the Cooley Field spigot
  • Began under-slab conduit to the transformer in the mechanical yard
  • Cut to subgrade in the North parking lot, formed and poured curb, and placed stone subbase
  • Began grading the bus loop subgrade
  • Set electrical switch gear on the house keeping pads

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

9/22/2017 – Construction Update

Work Performed this Week:

  • Started roof structural steel and joists in Unit B
  • Continued load-bearing masonry in Units A3, C, and D
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B2, A2, B1, and A1
  • Continued chilled water piping in the mechanical chases
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Resumed spray-applied polyurethane foam insulation (SPF) on the exterior of Units A, C, and D
  • Began veneer brick on the Unit A low roof
  • Completed the fire main to the mechanical room
  • Continued underground conduit across the bus loop for site lighting and power to out buildings
  • Cut to subgrade in the North parking lot
  • Electrical switch gear delivered

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

9/15/2017 – Construction Update

Work Performed this Week:

  • Continued load-bearing masonry in Units B3, C, and D
  • Poured the remainder of the Gathering Stairs
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1, A1, B2, and A2
  • Continued chilled water piping in Units A1, B1, and B2
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Continued fire main to the mechanical room
  • Installed underground conduit across the bus loop for site lighting and power to out buildings

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

9/8/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and joists in Units C and D
  • Continued load-bearing masonry in Units B3, C, and D
  • Poured a portion of the Gathering Stairs
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progresses
  • Continued hanging ductwork in Units B1, A1, B2, and started in Unit A2
  • Continued chilled water piping in Units A1 and B1
  • Completed the storm drain to SS#2-10
  • Resumed fire main along Longhill Road
  • Continued underground rough-in for site lighting in the East parking lot and poured the light pole bases

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

9/1/2017 – Construction Update

Work Performed this Week:

  • Completed structural steel, joists, and decking in Unit A3
  • Started structural steel in Unit C Auditeria
  • Continued load-bearing masonry in Units B3, C, and D
  • Continued forming the Gathering Stairs and installing reinforcing bar
  • Poured the elevated deck in Unit A3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1, A1, and B2
  • Continued above ceiling electrical rough-in in Units B2 and A2
  • Continued chilled water piping in Units A1 and B1
  • Continued installing sprinkler pipe, drops, and heads in Unit A1
  • Backfilled the new curb in the East parking lot
  • Relocated contractor parking to the East parking lot
  • Continued underground rough-in for site lighting in the East parking lot
  • Continued asphalt demolition along Longhill Road
  • Resumed storm system from SS#2-9 toward SS#2-10

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.