10/27/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began roof steel and joists in Unit A
  • Continued installing roof deck in the Unit C locker rooms
  • Continued exterior metal framing on the high walls on the gymnasium
  • Continued load-bearing masonry in Units A, B3, and C
  • Continued exterior brick veneer in Unit B1
  • Continued installing clips for the exterior composite wall panels on the high walls of the gymnasium
  • Roofing material delivered for Unit B
  • Continued installing sprinkler pipe in Unit B3
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B1 and B3
  • Cooling towers delivered
  • Continued above ceiling domestic water piping in Units B and A
  • Continued electrical above ceiling rough-in in Units B3
  • Placed subbase stone in the bus loop
  • Installed rain leaders from Unit B to storm structure SS#2-10
  • Made the final domestic water connection at the building

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/20/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Continued installing roof deck in the Unit C locker rooms
  • Continued exterior metal framing on the high walls on the gymnasium
  • Continued load-bearing masonry in Units A, B3, and C
  • Continued exterior brick veneer in Unit B1
  • Began installing clips for the exterior composite wall panels on the high walls of the gymnasium
  • Continued installing sprinkler pipe in Units B2 and A2
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units A1 and B3
  • Continued above ceiling domestic water piping in Units B and A
  • Continued electrical above ceiling rough-in in Units B3
  • Continued grading the bus loop subgrade
  • Installed rain leaders from Unit B to storm structure SS#2-10

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/13/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began installing roof decking in Unit C locker rooms
  • Continued exterior metal framing
  • Continued load-bearing masonry in Units A3 and B3
  • Started installing sprinkler pipe in Units B2 and A2
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Unit C in the gymnasium
  • Continued above ceiling domestic water piping in Units B1 and A1
  • Chillers were delivered and set in the mechanical room
  • Set mechanical equipment curbs on the mechanical room roof
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Continued rough-in in the main electrical room in Unit C
  • Continued grading the bus loop subgrade

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

10/5/2017 – Construction Update

Work Performed this Week:

  • Continued structural steel and roof decking in Unit B
  • Began exterior metal framing in Unit B
  • Continued load-bearing masonry in Units A3, C, and D
  • Continued veneer brick on the Unit A low roof
  • Continued mechanical, electrical, and plumbing wall rough-in as masonry work progressed
  • Continued hanging ductwork in Units B2, A2, B1, and A1
  • Completed chilled water piping in the mechanical chases through the third floor
  • Continued domestic water piping in Units B3, C, and D
  • Continued electrical above ceiling rough-in in Units B2 and A2
  • Completed the domestic water line to the mechanical room
  • Installed the domestic water pipe to the Cooley Field spigot
  • Installed the storm structure and pipe at SS#3-2 near Longhill Road
  • Continued under-slab rough-in in the mechanical yard
  • Continued grading the bus loop subgrade

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.