2/19/2018 – Construction Update

Work Performed this Week:

  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued interior non-bearing CMU walls throughout
  • Continued adjusting the operable partition wall support steel in Unit B
  • Installed structural steel at the student entrance canopy
  • Installed steel in Stair AS-3
  • Installed railings in Stair BS-1
  • Continued exterior framing in the Auditeria and Food Service parapet
  • Continued installing exterior windows in Unit A1
  • Continued PVC roofing in Units A and C
  • Continued installing framing and cleats for the exterior composite wall panels in Unit B
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB3, AB2, and B1
  • Continued priming and painting the walls in Units AB3 and AB2
  • Pulled and connected main electrical feeder wire from the switchgear to the primary electrical panels
  • Continued hanging VAVs and ductwork in Units A, B, C, and D
  • Insulated low and medium pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit B in interior CMU walls
  • Continued steel hydronic piping in Unit C
  • Began installing ceiling grid in Unit B3

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

2/12/2018 – Construction Update

Work Performed this Week:

  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued chase wall CMU in Unit B
  • Continued adjusting the operable partition wall support steel in Unit B
  • Installed steel framing in Stair AS-3
  • Installed railings in Stair BS-1
  • Continued exterior framing in the Auditeria and Food Service parapet
  • Continued installing exterior windows in Unit B
  • Continued installing the curtainwall framing in Unit B
  • Continued PVC roofing in Unit A above the research commons
  • Continued installing framing and cleats for the exterior composite wall panels in Unit C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB2 and B1
  • Continued priming and painting the walls in Units AB3 and AB2
  • Continued wall and above ceiling rough-in and pulling wire in Units A and B
  • Set rooftop air handling units on the roofs of Units C and D
  • Continued hanging VAVs and ductwork in Units A, B, C, and D
  • Insulated low pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit B in interior CMU walls
  • Continued steel hydronic piping in Unit C

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

2/2/2018 – Construction Update

Work Performed this Week:

  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued chase wall CMU in Unit B
  • Continued installing the operable partition wall support steel in Unit B
  • Installed the remaining roof decking above Food Services and Fitness Lab
  • Install steel columns and beams at the student entrance canopy
  • Installed steel framing in Stair AS-3
  • Continued exterior framing in the Auditeria and Food Service parapet
  • Continued installing exterior windows in Unit A
  • Began installing the curtainwall framing in Unit B
  • Continued PVC roofing above the Gathering Stairs
  • Continued installing wall clips and framing for the exterior composite wall panels in Unit C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB2 and B1
  • Continued priming and painting the walls in Units AB3 and AB2
  • Continued wall and above ceiling rough-in and pulling wire in Units A and B
  • Set rooftop air handling units on the Unit B roof
  • Continued hanging VAVs and ductwork in Units A, B, C, and D
  • Insulated low pressure ductwork in Units AB3 and AB2
  • Continued domestic water supply piping in Unit B in interior CMU walls
  • Continued steel hydronic piping in Unit C

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

1/26/2018 – Construction Update

Work Performed this Week:

  • Poured concrete treads and landings in Stair BS-1
  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued chase wall CMU in Unit B
  • Continued installing the operable partition wall support steel in Unit B
  • Continued roof steel above the student entrance and throughout Unit D
  • Continued exterior framing in Units A and C along the parapet and high walls
  • Continued installing exterior windows in Unit A
  • Continued spray polyurethane foam insulation on the exterior walls in Units A, B and C
  • Continued PVC roofing in Unit D
  • Continued installing wall clips and framing for the exterior composite wall panels in Units A and C
  • Continued priming and painting the framed walls in Unit B3
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Unit B2
  • Continued wall and above ceiling rough-in and pulling wire in Units A and B
  • Continued hanging VAVs and ductwork in Units A and B
  • Insulated low pressure ductwork in Unit B3
  • Continued domestic water supply piping in Unit B
  • Continued steel hydronic piping in Unit C
  • Pulled low voltage wiring in Unit B3
  • Installed and pressurized the Virginia Natural Gas service line

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.