Work Performed this Week:

  • Poured concrete treads and landings in Stair BS-1
  • Continued brickwork on the West and South elevations in Unit C and D
  • Continued chase wall CMU in Unit B
  • Continued installing the operable partition wall support steel in Unit B
  • Continued roof steel above the student entrance and throughout Unit D
  • Continued exterior framing in Units A and C along the parapet and high walls
  • Continued installing exterior windows in Unit A
  • Continued spray polyurethane foam insulation on the exterior walls in Units A, B and C
  • Continued PVC roofing in Unit D
  • Continued installing wall clips and framing for the exterior composite wall panels in Units A and C
  • Continued priming and painting the framed walls in Unit B3
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Unit B2
  • Continued wall and above ceiling rough-in and pulling wire in Units A and B
  • Continued hanging VAVs and ductwork in Units A and B
  • Insulated low pressure ductwork in Unit B3
  • Continued domestic water supply piping in Unit B
  • Continued steel hydronic piping in Unit C
  • Pulled low voltage wiring in Unit B3
  • Installed and pressurized the Virginia Natural Gas service line

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.