Work Performed this Week:

  • Continued interior brick in Unit A1
  • Continued non-load bearing interior CMU walls in throughout
  • Poured the mechanical yard slab-on-grade and building entrance stoops
  • Completed the operable partition wall support steel in Unit B
  • Installed structural bracing at the top of CMU walls
  • Continued exterior framing and sheathing in Units A and C
  • Installed exterior composite wall panels and flashings in Unit B
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units AB3, AB2, and AB1
  • Continued priming and painting in Units B3 and B2
  • Continued final hydronic and duct connections to the VAVs in Units A and B
  • Continued hanging VAVs and ductwork in Units A, C, and D
  • Continued insulating low and medium pressure ductwork and risers in Units AB3 and AB2
  • Continued setting and welding steel hydronic piping in Unit C
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Continued installing ceiling grid in Unit B2
  • Dominion Energy re-inspected and confirmed the project is ready for installation of permanent power

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

[av_gallery ids=’17846,17847,17848,17849,17850,17851′ style=’thumbnails’ preview_size=’portfolio’ crop_big_preview_thumbnail=’avia-gallery-big-crop-thumb’ thumb_size=’square’ columns=’6′ imagelink=’lightbox’ lazyload=’deactivate_avia_lazyload’ custom_class=” admin_preview_bg=”]