4/23/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C 
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A 
  • Installed exterior composite wall panels and flashings in Units A, B, and C 
  • Continued setting windows in Unit A 
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A, B, and C 
  • Continued priming and painting in Units B and C 
  • Completed ceramic tile in the locker rooms and food service areas 
  • Continued final hydronic and duct connections to the variable air volume VAVs throughout 
  • Set the cooling towers on the support framing in the mechanical yard 
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D 
  • Continued hanging duct in food service 
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A, B, and C 
  • Continued setting and welding steel hydronic piping in Unit C mechanical room 
  • Installed lights in the ceiling grid in Units AB3 and AB2 
  • Installed occupancy sensors in Units A and B 
  • Pulled fire alarm wiring in Units A and B 
  • Continued trimming out electrical work in Units AB3 and AB2 
  • Continued electrical rough-in in the mechanical room and gymnasium 
  • Continued installing ceiling grid in Units AB2 and B1 
  • Permanent power connected and meter set 
  • Permanent service line connected and meter set 
  • Began installing science lab casework 
  • Began installing gymnasium equipment 
  • Installed the cooler and freezer in food service 
  • Sitework resumed with sidewalks poured in the East parking lot 
  • Bus fuel tank pad formed and ready for the concrete 
  • Continued pulling data wiring in Unit B1 

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/9/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls throughout
  • Continued exterior framing and sheathing in Unit A
  • Installed exterior composite wall panels and flashings in Units A, B, and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs throughout
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Hung duct in Food Service
  • Continued insulating low and medium pressure ductwork and hydronic pipe in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Installed occupancy sensors in Units A and B
  • Pulled fire alarm wiring in Units A and B
  • Continued electrical rough-in in the mechanical room and gymnasium
  • Continued installing ceiling grid in Units AB2 and B1
  • Completed underground rough-in for the fuel pump
  • Set the new transformer and terminated conductor in the switchgear and new transformer
  • Set the electrical meter
  • Outage effecting the Central Office is scheduled between 5:00 am and 6:30 am on Monday, April 9, 2018 to make the final connection at the existing transformer and energize the new building
  • Set the gas meter

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.

4/2/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls in throughout
  • Continued exterior framing and sheathing in Unit A
  • Continued installing windows and curtainwall
  • Installed exterior composite wall panels and flashings in Units A and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A
    and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs in Units A and B
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Continued insulating low and medium pressure ductwork in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Pulled fire alarm wiring in Units A and B
  • Roughed-in electrical in the mechanical room
  • Continued installing ceiling grid in Unit AB2
  • Installed the range hoods
  • Installed the fuel tank for the buses
  • Pulled the underground conductor for permanent power

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.