4/2/2018 – Construction Update

Work Performed this Week:

  • Continued interior CMU and brick in Units A and C
  • Continued non-load bearing interior CMU walls in throughout
  • Continued exterior framing and sheathing in Unit A
  • Continued installing windows and curtainwall
  • Installed exterior composite wall panels and flashings in Units A and C
  • Continued interior framing, hanging gypsum board, sound insulation, and finishing in Units A
    and B
  • Continued priming and painting in Units B and C
  • Set ceramic tile in the locker rooms
  • Continued final hydronic and duct connections to the VAVs in Units A and B
  • Continued hanging variable air volume (VAV) boxes and ductwork in Units A, C, and D
  • Continued insulating low and medium pressure ductwork in Units A and B
  • Continued setting and welding steel hydronic piping in Unit C mechanical room
  • Installed lights in the ceiling grid in Units AB3 and AB2
  • Pulled fire alarm wiring in Units A and B
  • Roughed-in electrical in the mechanical room
  • Continued installing ceiling grid in Unit AB2
  • Installed the range hoods
  • Installed the fuel tank for the buses
  • Pulled the underground conductor for permanent power

Note: Areas D & C are the single-story section of the school. That includes the gym, cafeteria, kitchen, music, art, and fitness rooms. Areas A & B are the 3-story classroom sections.